Projects - Completed
Sisseton Health Center
| Location: |
Sisseton, SD |
|
|---|---|---|
| Current Working Estimate: |
$40.2 million |
|
| Construction Start Date: |
November 2003 |
|
| Construction Completion Date: |
March 2007 |
|
| Total Building Gross Area: |
7,615 M2 |
|
| Contract Type: |
Direct Federal (Design) |
PL 93-638 (Construction) |
| A/E Firm: |
Leo Daly |
|
| Prime Contractor: |
Gordon Construction |
This replacement health care facility, located in northeast South Dakota, was completed in March 2007. The 7,615 gross square meter facility provides a full array of ambulatory health care services including dialysis, dental, optometry, and audiology. Contract health services provide emergency, telemedicine, and inpatient services. The project will also include 62 staff quarters, which began construction in October 2006 and are scheduled for completion in the fall of 2010. The total project cost is between $40 to $45 million.